CATArithmetic > MediumEntered answer:✅ Correct Answer: 10Related questions:CAT 2020 Slot 3A contractor agreed to construct a 666 km road in 200200200 days. He employed 140140140 persons for the work. After 606060 days, he realized that only 1.51.51.5 km road has been completed. How many additional people would he need to employ in order to finish the work exactly on time?CAT 2018 Slot 2A water tank has inlets of two types AAA and BBB. All inlets of type AAA when open, bring in water at the same rate. All inlets of type BBB, when open, bring in water at the same rate. The empty tank is completely filled in 303030 minutes if 101010 inlets of type AAA and 454545 inlets of type BBB are open, and in 111 hour if 888 inlets of type AAA and 181818 inlets of type BBB are open. In how many minutes will the empty tank get completely filled if 777 inlets of type AAA and 272727 inlets of type BBB are open?CAT 2022 Slot 3Bob can finish a job in 404040 days, if he works alone. Alex is twice as fast as Bob and thrice as fast as Cole in the same job. Suppose Alex and Bob work together on the first day, Bob and Cole work together on the second day, Cole and Alex work together on the third day, and then, they continue the work by repeating this three- day roster, with Alex and Bob working together on the fourth day, and so on. Then, the total number of days Alex would have worked when the job gets finished, is